22. The following information is available for three MPS items:

Product A An 80-unit order is to be started in week 3.

Product A 55-unit order is to be started in week 6.
Product B A 125-unit order is to be started in week 5.
Product C A 60-unit order is to be started in week 4.

Develop the material requirements plan for the next 6 weeks for items D, E, and F. The BOMs are shown in Figure 16.41, and data from the inventory records are shown in Table 16.4. (Warning:A safety stock require- ment applies to item F. Be sure to plan a receipt for any week in which the projected on-hand inventory becomes less than the safety stock.)